A 42,000 sq ft warehouse addition with six new dock positions, delivered while shipping continued seven days a week.
What this covers
Live operations
Shipping never stopped; hoarding and traffic plans changed weekly.
Structure
Pre-engineered steel and tilt-panel envelope tied into the existing building.
Docks
Six levellers, seals and control panels commissioned in one weekend.
Result
Occupancy granted two weeks ahead of the tenant's peak season.



Included in the program
- 42,000 sq ft industrial addition
- Reinforced slab and trench drains for new equipment
- 800A electrical service upgrade and plant distribution
- Truck court, paving and drainage rebuild
- Phased occupancy with zero shipping days lost